AI Prompt for a Project Risk Register With a Worked Example

Build a project risk register from the evidence in your notes. Try the prompt on a pilot launch, then check whether it assigns the right owner and catches a risk that has already happened.

Copy the project risk register prompt

Give each source note a short ID before you paste it. Include the reporting date so a reviewer can tell whether an event was still uncertain when the register was prepared.

Build a project risk register as of [report date] using only the labeled notes below.
For each uncertain future event, record its source IDs, risk, potential impact, risk owner, response and response status, and next review date.
Use “unassigned” for an unknown owner and “unspecified” for missing information. Cite the note that supports each assigned owner or date.
Separate issues that have already occurred from future risks. Carry a related future consequence into the register only when the notes support it.
Distinguish accepted actions from proposals. Keep action owners separate from risk owners. Preserve conflicts as questions for review.
Do not infer likelihood, impact scores or dates. Return an empty register if the notes contain no supported future risk.
After the register, list current issues and questions for the next review.
Source notes:
[paste dated notes with IDs]

Try the prompt on five project notes

These fictional notes describe one pilot. Run them through the prompt and count how many open risks you get.

Pilot launch review, 26 November 2026
[N1] Supplier: “The scanner shipment may miss the pilot intake on 2 December. Without scanners, warehouse trials would start late.”
[N2] Ana: “I own the scanner delivery risk. I’ll review it on 30 November.”
[N3] Ben: “Could we borrow two scanners from the training team?” No decision was recorded.
[N4] Test lead: “The shared test account was locked this morning. Integration testing is already blocked.”
[N5] QA lead: “If the Saturday shift is short-staffed, we may miss the retest window. I will check the rota on Friday.”

Compare your result with the worked register

The reference answer records two open risks. Each entry below is one row in the downloadable register.

Scanner shipment may miss pilot intake

Source IDs
N1, N2, N3
Potential impact
Warehouse trials could start late
Risk owner
Ana
Response
Borrow two training scanners
Response status
Proposed
Next review
30 November 2026

Saturday shift may be short-staffed

Source IDs
N5
Potential impact
Retest window could be missed
Risk owner
Unassigned
Response
QA lead to check the rota on Friday
Response status
Committed
Next review
Unspecified

Download the risk register workbook (.xlsx)

Download the CSV version

Record the locked account as an issue

In N4, the account is already locked and testing has stopped. Log the observed blockage in the issue log. Ask who can restore access and when the team will check progress. The notes give neither detail.

Ben’s scanner suggestion in N3 deserves a different follow-up. Ask whether the training team has spares and who will arrange the loan. Until someone agrees, describing the scanners as secured would hide the delivery exposure.

Check ownership and dates before sharing

For the staffing risk, the QA lead accepted one action. The notes leave ownership of the overall risk open. Friday is the rota check date. The team still needs to set a risk review date. For the scanner risk, 2 December is the intake date and 30 November is Ana’s review date.

To test your prompt, remove N2 and run it again. The scanner risk should survive because N1 supports it. Its owner should become unassigned and its review date unspecified. If either value persists, rerun in a fresh conversation and check which source the answer cites.

Once owners confirm the register, use the project status report prompt to summarize the exposures that need sponsor attention.